Please be advised that NMDOH/OSAH has released the RFP for SBHC Services on April 1, 2019. It is included here. Some critical timelines are noted below, which includes mandatory submission of Receipt of RFP form on 4/8/19, deadline to submit written questions on 4/10/19, and submission of proposal by 3pm (MST) on 5/3/19. If you need technical assistance from NMASBHC, please reach out to us.
Thank you and good luck!
Excerpt from RFP:
The Procurement Manager will make every effort to adhere the following schedule:
Action Responsibility Date
Issue of RFP Agency 4/1/19
Distribution List Response Potential Offerors 4/8/19
Deadline to Submit Potential Offerors 4/10/18
Questions
Response to Written Agency 4/12/19
Questions/RFP Amendments
Submission of Proposal Offeror 5/3/19
Proposal Evaluation Evaluation Committee 5/15/19
Selection of Finalists Evaluation Committee 5/15/19
Best and Final Offers Offeror 5/17/19
From Finalists
Oral Presentation by Finalists Offeror 5/17/19
Finalize Contract Agency, Offeror 5/31/19
Contract Award State Purchasing Agent/DFA 7/1/19
Protest Deadline Offeror 7/15/19